Project Map

Please use the interactive map below to view project information.

County-wide projects:

Miscellaneous Sewer Rehabilitation:

This project continues our “find and fix” program of sanitary sewer rehabilitation to reduce infiltration and inflow (I&I) in our system during the fiscal year. This work will utilize the ACSA cooperative contracting language in the City rehabilitation contract that was recently awarded after competitive bidding. It will be used to make repairs and rehabilitate problems in our system found with systematic CCTV inspection by ACSA crews and the subcontractor. Total Budget: $400,000

SCADA System:

The ACSA Utility System has over 40 critical assets that include water and wastewater pump stations, water storage tanks and master PRV stations. This project will create a Supervisory Control and Data Acquisition (SCADA) System that will allow ACSA employees to remotely monitor the operations of these critical assets from the main office building. Using alarms we will be able to more quickly evaluate problems and prevent some failures before they happen. The first phase is complete and in operation. The second phase is currently under construction and is expected to be completed in FY 2017. The design of Phase 3 is nearing completion and construction is expected to be finished in FY 2018 using funds previously budgeted. Total Budget: $1,744,000

Advanced Metering Infrastructure Feasibility Study:

This project addresses a goal in our Strategic Plan to evaluate various AMI technologies in relation to our existing metering system, as well as, the compatibility of our existing billing system to convert to an AMI system. It will include a financial analysis, a potential implementation plan, and make recommendations. The study will provide the necessary information for further discussion and help the ACSA determine whether or not implementing an AMI system would better support the needs of our customers and staff into the future. Total Budget: $200,000

Developer Participation:

Each year funds are set aside to participate in oversizing utilities constructed to serve new development. The Rate Model includes $100,000 divided equally between water and wastewater projects as a contingency to insure the new pipes are sized to meet the ACSA’s long-range needs. Total Budget: $100,000